Question: A compression technique where you add extra resources (money, staff, workers, machinery-equipment,materials) to the project to compress (shorten) the schedule is called A. Slack B.
A compression technique where you add extra resources (money, staff, workers, machinery-equipment,materials) to the project to compress (shorten) the schedule is called
- A. Slack
- B. Duration
- C. Float
- D. Task dependency
- E. Crashing