Question: A computer system has recently been installed in the accounts department of a manufacturing company. The activities involved in introducing the system are listed below

A computer system has recently been installed in the accounts department of a manufacturing company. The activities involved in introducing the system are listed below together with their normal durations and costs. It would be possible to shorten the overall project duration by crashing certain activities at extra cost, so the relevant details are also included. In addition, there will be a weekly charge of $7000 to cover overheads.

Activity

Predecessor

Normal Time (weeks)

Normal Cost ($)

Crash Time (weeks)

Crash Cost ($)

A

-

3

2000

2

7000

B

-

6

5000

6

5000

C

A

4

8000

1

19000

D

B

2

1500

2

1500

E

A

8

4000

5

9000

F

B

4

3000

3

7000

G

C, D

2

2000

2

2000

H

F

3

3000

2

9000

a) What is the normal expected duration of the project? What is the critical path?

The normal expected duration of the project is: Answer
The critical path is: AnswerACGAEBDGBFH

b) What would be the cost of completing the project using the normal durations?

c) What would be the duration of the project if costs are to be minimized?

Activity

Maximum Crash Time (weeks)

Crash Cost/week

A

Answer

Answer

B

Answer

Answer

C

Answer

Answer

D

Answer

Answer

E

Answer

Answer

F

Answer

Answer

G

Answer

Answer

H

Answer

Answer

Stage

Crash Activity

Time Reduction (weeks)

Resulting Critical Path(s)

Project Duration (weeks)

Project Direct Costs ($)

Crash Cost ($)

Total Indirect Costs ($)

Total Project Costs ($)

0

AnswerABCDEFGHNone

Answer

AnswerACGAEBDGBFH

Answer

Answer

Answer

Answer

Answer

1

AnswerABCDEFGHNone

Answer

AnswerACGAEBDGBFH

Answer

Answer

Answer

Answer

Answer

2 AnswerABCDEFGHNone Answer AnswerACGAEBDGBFH Answer Answer Answer Answer Answer

Therefore the optimal project duration is Answer weeks, and the optimal project cost is $Answer.

sollve t on excel pls as soon as possible

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!