Question: A computer system has recently been installed in the accounts department of a manufacturing company. The activities involved in introducing the system are listed below
A computer system has recently been installed in the accounts department of a manufacturing company. The activities involved in introducing the system are listed below together with their normal durations and costs. It would be possible to shorten the overall project duration by crashing certain activities at extra cost, so the relevant details are also included. In addition, there will be a weekly charge of $7000 to cover overheads.
| Activity | Predecessor | Normal Time (weeks) | Normal Cost ($) | Crash Time (weeks) | Crash Cost ($) |
| A | - | 3 | 2000 | 2 | 7000 |
| B | - | 6 | 5000 | 6 | 5000 |
| C | A | 4 | 8000 | 1 | 19000 |
| D | B | 2 | 1500 | 2 | 1500 |
| E | A | 8 | 4000 | 5 | 9000 |
| F | B | 4 | 3000 | 3 | 7000 |
| G | C, D | 2 | 2000 | 2 | 2000 |
| H | F | 3 | 3000 | 2 | 9000 |
a) Determine ES, EF, LS, LF and slack for each activity
| Activity | Early start | Early Finish | Late Start | Late Finish | Slack |
| A | |||||
| B | |||||
| C | |||||
| D | |||||
| E | |||||
| F | |||||
| G | |||||
| H |
| B. What is the normal expected duration of the project is: | |
| C. The critical path is |
|
| D. What would be the cost of completing the project is using the normal distribution: | |
E What would be the duration of the project if costs are to be minimized?
| Activity | Maximum Crash Time (weeks) | Crash Cost/week |
| A | ||
| B | Answer | Answer |
| C | Answer | Answer |
| D | Answer | Answer |
| E | Answer | Answer |
| F | Answer | Answer |
| G | Answer | Answer |
| H | Answer | Answer |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
