Question: A- Consider a simple process where work flows from Activity A to Activity B to Activity C to Activity D. Activity A takes 3 minutes
A- Consider a simple process where work flows from Activity A to Activity B to Activity C to Activity D. Activity A takes 3 minutes and is performed by Aaron. Activity B takes 5 minutes and is performed by Aaron and Betty together. Activity C takes 4 minutes and is performed by Betty and David together. Activity D is performed by David and takes 3 minutes. What is the bottleneck of the process?
Group of answer choices
None of these
Activity B
Aaron
Betty
Activity C
For the project network described in Question 8,
B- An activity on the project network has a slack time of 2 days. Which of the following is NOT true?
Group of answer choices
Increasing the activity time by 2 days would make this activity critical for the project.
Increasing the activity time by 2 days would increase its slack time by 2 days.
Increasing the activity time by 2 days would decrease its slack time by 2 days.
Increaseing the activity time by more than 2 days would increase the project duration.
HELP ME SOLVE THIS