Question: Consider a simple process where work flows from Activity A to Activity B to Activity C to Activity D. Activity A takes 3 minutes and
Consider a simple process where work flows from Activity A to Activity B to Activity C to Activity D. Activity A takes 3 minutes and is performed by Aaron. Activity B takes 5 minutes and is performed by Aaron and Betty together. Activity C takes 4 minutes and is performed by Betty and David. Activity D is performed by David and takes 3 minutes. What is the bottleneck of the process?
1) None of these
2) Activity A
3) Activity C
4) Activity B