Question: A) Consider the Problem #5 for the following questions. a)What is the maximum number of horse sculptures Keuka can make per hour? b)What is the

A) Consider the Problem #5 for the following questions.
a)What is the maximum number of horse sculptures Keuka can make per hour?
b)What is the utilization (%) of the lathe (assume flow rate equal capacity of lathe)?
(you number should look like this: 44.55 for 44.55%)
c)Suppose Keuka is demand-constrained and they have 1 worker who is able to assemble a horse sculpture in 16 minutes. What is the average inventory of Body parts?
Keuka Studies does custom metal sculptures of horses and other animals. A horse sculpture is composed of numerous parts. They use a lathe to construct two types of parts. The "Body" part is used to support the torso of the horse and the "Leg" part is used to support the legs. Each horse sculpture needs 1 Body part and 4 Leg parts. Switching between either of the types of parts requires 25 minutes. Once ready to produce, the lathe produces a Body part in 4 minutes and a single Leg part in 2 minutes. The lathe only makes horse parts. For parts (a)-(d) assume Keuka operates a cyclic schedule in which they make 100 Body parts and then 400 Leg parts. Furthermore, assume the lathe is the bottleneck
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock