Question: a. construct a network diagram b. calculate ES, LS, EF, LF times for each activity c. determine critical path d. what is the duration of

a. construct a network diagram
b. calculate ES, LS, EF, LF times for each activity
c. determine critical path
d. what is the duration of the critical path.
Question No: 05 Activity Predecessor Duration (weeks) 9 B A 2 A 12 D A 5 E B 6 F B 8 G C, F 3 H D 2 1 H 8 J GI 6 K E. 2 ResnonceStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts