Question: The activities of a complex project with predecessors are given below. Activity Predecessor Duration(Weeks) A ----- 9 B A 2 C A. 12 D A
The activities of a complex project with predecessors are given below.
Activity Predecessor Duration(Weeks)
A ----- 9
B A 2
C A. 12
D A 5
E B 6
F B 8
G C,F 3
H D 2
I H 8
J G,I 6
K E,J 2
a) Construct a network diagram
b) Calculate ES, LS, EF, LF for each activity.
c) Determine critical path.
d) What is the duration of critical path?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
