Question: A construction contractor finished a bridge across a river 1 2 months early and received more than $ 5 million for the early completion. This

A construction contractor finished a bridge across a river 12 months early and received more than $5 million for the early completion. This is an example of reducing project duration caused by
Group of answer choices
imposed project deadlines.
time to market
unforeseen project delays
high overhead
incentive contracts