Question: A construction project has a Budget At Completion ( BAC ) of $ 1 , 0 0 0 , 0 0 0 , and a

A construction project has a Budget At Completion (BAC) of $1,000,000, and a scheduled duration of 300 days. On day 100 of the project, 36% of the work is completed and $300,000 has been spent. What is the budget and schedule status of this project?
Question 13 options:
Over budget and behind schedule
Over budget and ahead of schedule
Under budget and behind schedule
Under budget and ahead of schedule

Step by Step Solution

There are 3 Steps involved in it