Suppose you have a project with a Budget at Completion (BAC) of $250,000 and a projected length

Question:

Suppose you have a project with a Budget at Completion (BAC) of $250,000 and a projected length of 10 months. After tracking the project for six months, you have collected the information in the table below.
Suppose you have a project with a Budget at Completion

a. Complete the table. How do Earned Value SPI (based on $) and Earned Schedule SPI differ?
b. Calculate the scheduled variance for the project for both Earned Value and Earned Schedule. How do the values differ?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: