Question: A Construction Project has indirect costs totaling Rs . 4 0 , 0 0 0 per week. The major activities in the project and their
A Construction Project has indirect costs totaling Rs per week. The major activities in the project and their expected times are shown in the TABLE below :
Activity Expected Time
in weeks CRASHING COSTS Rs
First Week Second Week Third Week
a Determine the optimum timecost crashing plan.
b Tabulate the total cost values and find the least expensive crashing schedule that would reduce the project duration by six weeks
A project at Day exhibits percent progress, when percent was planned for an effective date of Planned cost was Rs at Day and Rs at Day and actual cost was Rs at Day and Rs at day Find the time variance,
cost variance and schedule varianc
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
