Question: A Construction Project has indirect costs totalling Rs . 4 0 , 0 0 0 per week. The major activities in the project and their
A Construction Project has indirect costs totalling Rs per week. The major activities in the project and their expected times are shown in the TABLE below:
Activity Expected Time CRASHING COSTS RS
in weeksst Week nd Week rd Week
a Determine the optimum timecost crashing plan.
bTabulate the total cost values and find the least expensive crashing schedule that would reduce the project duration by six weeks.