Question: A Construction Project has indirect costs totalling Rs . 4 0 , 0 0 0 per week. The major activities in the project and their

A Construction Project has indirect costs totalling Rs.40,000 per week. The major activities in the project and their expected times are shown in the TABLE below: (12)
Activity Expected Time CRASHING COSTS (RS.'000)
(in weeks)1st Week 2nd Week 3rd Week
1-251822--
2-58242525
5-77303035
7-1141520--
11-1311303336
1-34122426
3-812------
8-115404040
3-9631012
9-1292710
12-13126----
1-43101525
4-612813--
6-109512--
10-1281415--
a. Determine the optimum time-cost crashing plan.
b.Tabulate the total cost values and find the least expensive crashing schedule that would reduce the project duration by six weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!