Question: A construction project has indirect ( overhead ) costs as $ 6 0 per day. Based on the details in the table below, calculate the

A construction project has indirect (overhead) costs as $60 per day. Based on the details in the table below, calculate the optimum schedule and minimum total cost for the project.
\table[[Activity,IPA,Normal,Crash],[\table[[Duration],[(days)]],Cost ($),\table[[Duration],[(days)]],Cost ($)],[A,-,2,120,2,-],[B,A,5,180,4,240],[C,B,6,170,4,190],[D,B,7,150,5,185],[E,C, D,4,190,3,240]]
A construction project has indirect ( overhead )