Question: A construction project has the following activity information: Duration (weeks) Activity Optimistic Most Likely Immediate Prodecessors Pessimistic A 16 28 B 4 19 25 10

A construction project has the following activity
A construction project has the following activity information: Duration (weeks) Activity Optimistic Most Likely Immediate Prodecessors Pessimistic A 16 28 B 4 19 25 10 18 37 D B 13 37 E BC 13 19 33 F B 19 22 33 G DE 4 7 19 H F G 13 19 49 B.C 13 25 37 LH 13 19 1 Draw the notwork 2 Identify the critical path 3. Determine the probability of completing the project in 104 weeks b: 100 weeks