Question: Project Activity Information Activity Immediate Predecessors Optimistic (weeks) Most Likely (weeks) Pessimistic (Weeks) A 3 4 5 B A 4 5 12 C 2 4
| Project Activity Information |
| |||||
| Activity | Immediate Predecessors | Optimistic (weeks) | Most Likely (weeks) | Pessimistic (Weeks) |
| |
| A | 3 | 4 | 5 | |||
| B | A | 4 | 5 | 12 | ||
| C | 2 | 4 | 6 | |||
| D | C | 3 | 4 | 5 | ||
| E | B, D | 1 | 2 | 3 | ||
| F | E | 2 | 4 | 6 | ||
| G | B, D | 6 | 7 | 14 | ||
| H | G | 6 | 8 | 10 | ||
| I | F, H | 3 | 4 | 5 | ||
| Marketing Data from Ad Agency | ||
| Type of Advertisement | Exposure per Ad | Cost per Ad |
| TV ads 1-6 | 12,000 | 30,000 |
| TV ads 7 and over | 4,500 | 30,000 |
| Radio ads 1-12 | 6,000 | 9,000 |
| Radio ads 13 and over | 3,600 | 9,000 |
| Online ads 1-18 | 3,000 | 4,000 |
| Online ads 19 and over | 2,400 | 4,000 |
| Game | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| Probability the Steelers Win | 0.55 | 0.6 | 0.45 | 0.4 | 0.65 | 0.55 | 0.45 | 0.7 |
The owner of Steel City has hired you to help with the three tasks described above. Specifically, the owner has two requests:
- Develop some metrics surrounding the reorganization project. They want to visualize the project map, and better understand the timeline of the project. In particular, the owner is very concerned about the finish date of the project and wants to know the expected completion time and how far in advance the project should be completed in order to assure a .95 probability of completing the project on time (assuming project finish times follow a normal distribution).
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts