Question: A construction project involves the following tasks with their respective durations ( in days ) and dependencies: Task A: 4 days ( no dependencies )
A construction project involves the following tasks with their respective durations in days and dependencies:
Task A: days no dependencies
Task B: days depends on Task A
Task C: days depends on Task A
Task D: days depends on Task B
Task E: days depends on Task C
Task F: days depends on Tasks D and E
What is the critical path and the total project duration?