Question: A construction project involves the following tasks with their respective durations ( in days ) and dependencies: Task A: 4 days ( no dependencies )

A construction project involves the following tasks with their respective durations (in days) and dependencies:
Task A: 4 days (no dependencies)
Task B: 6 days (depends on Task A)
Task C: 5 days (depends on Task A)
Task D: 3 days (depends on Task B)
Task E: 2 days (depends on Task C)
Task F: 4 days (depends on Tasks D and E)
What is the critical path and the total project duration?