I would like to see a network diagram with the answers to the questions. You are managing
Fantastic news! We've Found the answer you've been seeking!
Question:
I would like to see a network diagram with the answers to the questions. You are managing a project that consists of the following tasks: Task A: Duration: 4 days, no predecessors Task B: Duration: 3 days; predecessor is A Task C: Duration: 6 days; predecessor is A Task D: Duration: 2 days; predecessor is B Task E: Duration: 5 days; predecessors are B and C Task F: Duration: 2 days; predecessor is D Task G: Duration: 3 days; predecessor is E Task H: Duration: 2 days; predecessors are F and G Answer the following questions:
What is the critical path of the project? What is the duration of the project based on the critical path? Identify the free float and total float for Task F.