Question: A construction project is broken down into the following 8 activities: table [ [ Activity , Immediate predecessor,Time ( days ) ] , [

A construction project is broken down into the following 8 activities:
\table[[Activity,Immediate predecessor,Time (days)],[A,-,2],[B,A,5],[C,A,4],[D,B,1],[E,C,D,6],[F,D,3],[G,F,2],[H,E,G,4]]
(c) What is the slack of activity C?