Question: Det A construction project is broken down into the following 8 activities: Activity Immediate predecessor Time (days) A 4 B 2 A 4 D 3

Det A construction project is broken down into
Det A construction project is broken down into
Det A construction project is broken down into the following 8 activities: Activity Immediate predecessor Time (days) A 4 B 2 A 4 D 3 E BD 5 F D 02 G E N H F G 3 a. What is the project completion time in days? O 21 days O 17 days O 26 days 15 days