Question: A construction project is carried out by a general contractor with the following descriptions: Project Duration: 3 months (Start: May 1st; End: July 31st) Contract
A construction project is carried out by a general contractor with the following descriptions: Project Duration: 3 months (Start: May 1st; End: July 31st) Contract Amount: 29,000+36,000+56,000+46,000+61,000+75,000+39,000+105,000+151,000 Budget Amount: 108,000+200,000+304,000 Contract Terms and Conditions Materials: The construction company pays material suppliers in full when it receives payment from the owner. On the last day of each month the construction company may bill the owner for the work completed during the month. The owner pays the monthly bills one month after they are received. Labor: The construction company pays for labor on the 25th of each month. Subcontractor: The construction company pays subcontractors when it receives payment from the owner but withholds 5% from the subcontractor’s payment. Final payment will include payment of the retention. Between the contractor and the owner: On the last day of each month the construction company may bill the owner for the work completed during the month. The owner pays the monthly bills one month after they are received. -Labor: The construction company pays for labor on the 25th of each month. -Subcontractor: The construction company pays subcontractors when it receives payment from the owner but withholds 5% from the subcontractor’s payment. Final payment will include payment of the retention. -Between the contractor and the owner: On the last day of each month the construction company may bill the owner for the work completed during the month. The owner pays the monthly bills one month after they are received. The owner withholds 5% from the construction company's payment. Final payment will include payment of the retention. Cost-loaded schedule and billing schedule to the owner What is the amount of cash to maintain a positive cash flow in this project?Month May June July Cost-Loaded Schedule Materials 20,596 30,837 50,619 Labor 40,829 60,962 70,027 Subcontractor 30,469 100,819 154,727 Bill to Owner 100,026 200,678 300,929
Step by Step Solution
3.50 Rating (160 Votes )
There are 3 Steps involved in it
Statement showing the amount of Cash to maintain a positive cash flow in the project Particulars May ... View full answer
Get step-by-step solutions from verified subject matter experts