Question: A construction project's critical path describes: the delivery route for materials the bidding process for construction services. the cheapest way in which a project can
A construction project's critical path describes:
the delivery route for materials
the bidding process for construction services.
the cheapest way in which a project can be completed.
the fastest time in which a project can be completed.
a project's maximum duration.