Question: A construction project's critical path describes: the fastest time in which a project can be completed. the cheapest way in which a project can be

A construction project's critical path describes: the fastest time in which a project can be completed. the cheapest way in which a project can be completed. the delivery route for materials. the bidding process for construction services . a project's maximum duration.