Question: A contingency amount can be:Pick the wrong answer A . applied to individual activities or work packages B . applied to the project as a
A contingency amount can be:Pick the wrong answer
A applied to individual activities or work packages
B applied to the project as a whole
C continually increased to cover cost escalation
D all of the above
E a and b only.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
