Question: A contractor is building a small office building. The contract has a fixed price of $ 5 0 0 , 0 0 0 with materials
A contractor is building a small office building. The contract has a fixed price of $ with materials costing $ and labour costing $ The planned duration for the project is weeks, and the work rate is to complete of the project each week. Project Budget and Duration: BAC Budget at Completion: $ Planned Duration: weeks Status at Week : Actual Cost AC: $ Earned Value EV: $ Planned Value PV: $a Calculate the estimated cost of the project at completion along with the estimated duration of the project. Marksb Is the project over or under budget? Mark
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
