Question: A contractor is building a small office building. The contract has a fixed price of $ 5 0 0 , 0 0 0 with materials

A contractor is building a small office building. The contract has a fixed price of $500,000 with materials costing $300,000 and labour costing $200,000. The planned duration for the project is 20 weeks, and the work rate is to complete 5% of the project each week. Project Budget and Duration: BAC (Budget at Completion): $500,000 Planned Duration: 20 weeks Status at Week 10: Actual Cost (AC): $260,000 Earned Value (EV): $225,000 Planned Value (PV): $250,000(a) Calculate the estimated cost of the project at completion along with the estimated duration of the project. (2 Marks)(b) Is the project over or under budget? (1 Mark)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!