Question: Question 1 ( 3 Marks ) : A contractor is building a small office building. The contract has a fixed price of (

Question 1(3 Marks):
A contractor is building a small office building. The contract has a fixed price of \(\$ 500,000\) with materials costing \(\$ 300,000\) and labour costing \(\$ 200,000\). The planned duration for the project is 20 weeks, and the work rate is to complete \(5\%\) of the project each week.
Project Budget and Duration:
- BAC (Budget at Completion): \(\$ 500,000\)
- Planned Duration: 20 weeks
Status at Week 10:
- Actual Cost (AC): \$260,000
- Earned Value (EV): \$225,000
- Planned Value (PV): \(\$ 250,000\)
(a) Calculate the estimated cost of the project at completion along with the estimated duration of the project. (2 Marks)
(b) Is the project over or under budget? (1 Mark)
Question 1 ( 3 Marks ) : A contractor is building

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!