Question: A contractor sends a final billing report to a city requesting payment on a new fire station. City personnel inspect the building and approve payment
A contractor sends a final billing report to a city requesting payment on a new fire station. City personnel inspect the building and approve payment of the accumulated retainage of $8 million. The total amount billed to the city for the project was $80 million. Which account and amount is debited to record the payment of the retainage to the contractor in a Capital Projects Fund?
Select one:
a. Expenditures - construction cost is debited for $72 million.
b. Expenditures - construction cost is debited for $8 million.
c. Retainage payable should be debited for $72 million.
d. Retainage payable should be debited for $8 million.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
