Question: A contractor submits a payment requisition for certification by the CM . ? Everything seems to be in order except that the schedule of values
A contractor submits a payment requisition for certification by the CM ? Everything seems to be in order except that the schedule of values contains a new item for a Change Order that was submitted but has not been approved by the owner. What should the CM do
A ?Advise the contractor to revise the payment and resubmit within ?hours
B ?Approve the whole payment pending approval of change order by owner
C ?Reject the entire payment requisition and require resubmission
D ?Revise pay requisition to deduct value of change order not approved