Question: a) Create a Work Breakdown Structure (WBS) that lists all the steps to complete the project based on this project schedule: Task Description Duration (Days)
a) Create a Work Breakdown Structure (WBS) that lists all the steps to complete the project based on this project schedule:
| Task | Description | Duration (Days) | Predecessor Tasks |
| A | Project initiation | 1 | - |
| B | Determine user requirements | 3 | A |
| C | Feasibility analysis | 4 | A |
| D | Management presentation | 1 | B, C |
| E | System design | 3 | D |
| F | Development | 14 | E |
| G | Test system | 5 | F |
| H | Deployment | 1 | G |
WBS can be hand-drawn or using a suitable software application.
b) Develop PERT/CPM chart explaining the early and late start for each task. Identify the critical path and the total time to finish the project based on this project schedule. PERT/CPM chart must be created using a suitable software application such as draw.io.