Question: A crew of 5 bricklayers and 3 helpers construct a CMU partition that is 150 ft long and 11 ft high. What is the labor
A crew of 5 bricklayers and 3 helpers construct a CMU partition that is 150 ft long and 11 ft high. What is the labor cost if the productivity rate is 0.11 labor hours/sf bricklayers cost $40.30/hr and helpers cost $29.30/hr?