Question: A critical path in a project schedule refers to the: a ) Longest sequence of activities b ) Shortest sequence of activities c ) Activities

A critical path in a project schedule refers to the:
a) Longest sequence of activities
b) Shortest sequence of activities
c) Activities with the most resources allocated
d) Sequence of activities with zero slack time