Question: ? _ _ _ _ - a ctivities must b e completed immediately before a particular activity. Question 6 options: Merge Parallel Predecessor Burst Successor
ctivities must completed immediately before a particular activity.
Question options:
Merge
Parallel
Predecessor
Burst
Successor