Question: A decision maker is provided with 5 different potential projects and must determine which projects to choose. The projects require different amounts of capital and
A decision maker is provided with 5 different potential projects and must determine which projects to choose. The projects require different amounts of capital and different expected net present values (NPV) over the next three years. NVP Capital Required (in $000s) Project (in $000s) Year 1 Year 2 Year 3 1 140 70 20 25 2 180 85 40 15 3 120 60 20 20 4 80 30 30 15 5 200 50 15 10 Determine which set of projects should be selected in order to achieve the maximum net present value if the decision maker has $150,000 available for investment each year