Question: A deck building project is estimated to cost $ 5 0 , 0 0 0 with a timeline of 2 0 days. After 1 0

A deck building project is estimated to cost $50,000 with a timeline of 20 days. After 10 days, the project manager finds that 80% of the project is complete and Actual costs are $50,000. What is the Cost Performance Index (CPI)?
(A)0.5
(B)1
0.8
(D)1.6
 A deck building project is estimated to cost $50,000 with a