Question: a) Determine the new Estimated Time to Completion given the indicated state of the project (round your answers into TWO (2) decimal places). Identify the

a) Determine the new Estimated Time to Completion given the indicated state of the project (round your answers into TWO (2) decimal places).
Identify the new Estimated Cost to Completion for the project (round your answers into TWO (2) decimal places).
3. Project "Helo Helo Pappi Pollo" is estimated to complete within FIVE (5) months. However, after five months, the project is yet to be completed. Based on the earned value Table 2.0 below, answer the following questions: Tahle 2 n. Proient "Holn Holn Panni Polln" a) Determine the new Estimated Time to Completion given the indicated state of the project (round your answers into TWO (2) decimal places). (4 Marks) b) Identify the new Estimated Cost to Completion for the project (round your answers into TWO (2) decimal places). (4 Marks) 3. Project "Helo Helo Pappi Pollo" is estimated to complete within FIVE (5) months. However, after five months, the project is yet to be completed. Based on the earned value Table 2.0 below, answer the following questions: Tahle 2 n. Proient "Holn Holn Panni Polln" a) Determine the new Estimated Time to Completion given the indicated state of the project (round your answers into TWO (2) decimal places). (4 Marks) b) Identify the new Estimated Cost to Completion for the project (round your answers into TWO (2) decimal places). (4 Marks)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
