Question: Given the operation times below in a two-work-centre flow shop: a. Develop a job sequence that minimizes total idle time at the two work centres.
Given the operation times below in a two-work-centre flow shop:
a. Develop a job sequence that minimizes total idle time at the two work centres.
b. Construct a Gantt chart for the activities at the two work centres, and determine work centre 2€™s idle time.
Job Times (minutes) A D E Work Centre 1 20 16 43 60 35 42 Work Centre 2 27 30 51 12 28 24
Step by Step Solution
There are 3 Steps involved in it
Minimizing make time Johnsons rule minimizes make time The rule starts with f... View full answer