Question: Given the operation times provided: a. Develop a job sequence that minimizes idle time at the two work centers. b. Construct a chart of the
Given the operation times provided:
.png)
a. Develop a job sequence that minimizes idle time at the two work centers.
b. Construct a chart of the activities at the two centers, and determine each one’s idle time, assuming no other activities areinvolved.
JOB TIMES (minutes) Center 20 16 43 60 3 42 Center 227 30 5 1228 24
Step by Step Solution
3.48 Rating (164 Votes )
There are 3 Steps involved in it
a Develop a job sequence that minimizes idle time at the two work centers We will use Johnsons rule ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
372-B-M-L-O-M (3448).docx
120 KBs Word File