Question: a) Develop gross requirements plan for Items C. To do so, first find the gross requirements plans for its parents: items A and H. (Enter
a) Develop gross requirements plan for Items C. To do so, first find the gross requirements plans for its parents: items A and H. (Enter your responses as whole
numbers).
| Week | |||||||||||||
| Item | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | |
| A | Gross req | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | |||||||
| Order req. | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here |
| H | Gross req | enter your response here | enter your response here | enter your response here |
| Order req. | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here |
| C | Gross req | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here |
| Order req. | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here |
Develop a net requirements plan for Item C.
First find the net requirements plans for its parents: items A and H. Determine the net requirements plan for item A (enter your responses as whole
numbers).
| Level: 0 | Parent: | Quantity: | |||||||||||
| Item: A | Lead Time: 1 | Lot Size: L4L | |||||||||||
| Week | |||||||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | ||
| Gross requirements | 100 | 70 | 160 | ||||||||||
| Projected on-hand inventory | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here |
| Net requirements | enter your response here | enter your response here | enter your response here | ||||||||||
| Planned order receipts | enter your response here | enter your response here | enter your response here | ||||||||||
| Planned order releases | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here |
Determine the net requirements plan for item H (enter your responses as whole
numbers).
| Level: 0 | Parent: | Quantity: | |||||||||||
| Item: H | Lead Time: 1 | Lot Size: L4L | |||||||||||
| Week | |||||||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | ||
| Gross requirements | 90 | 40 | |||||||||||
| Projected on-hand inventory | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | enter your response here | enter your response here | enter your response here | enter your response here |
| Net requirements | enter your response here | enter your response here | |||||||||||
| Planned order receipts | enter your response here | enter your response here | |||||||||||
| Planned order releases | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here |
Determine the net requirements plan for item C (enter your responses as whole
numbers).
| Level: 1 | Parent: A&H | Quantity: 1X&1X | |||||||||||
| Item: C | Lead Time: 2 | Lot Size: L4L | |||||||||||
| Week | |||||||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | ||
| Gross requirements | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | ||||||||
| Projected on-hand inventory | 70 | 70 | 70 | 70 | 70 | 70 | 70 | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here |
| Net requirements | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | ||||||||
| Planned order receipts | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here |
| Planned order releases | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here |