Question: a) Develop a gross requirements plan for Items C. To do so, first find the gross requirements plans for its parents: items A and H.



a) Develop a gross requirements plan for Items C. To do so, first find the gross requirements plans for its parents: items A and H. (Enter your responses as whole
numbers).
b) Develop a net requirements plan for Item C.
First find the net requirements plans for its parents: items A and H. Determine the net requirements plan for item A (enter your responses as whole
numbers).
| 9 11 Period Gross requirements: A Gross requirements: H | | 10 60 12 140 90 80 40 Item Lead Time Item 1 Lead Time 2 1 On Hand 15 90 40 45 85 B C NNN OIX On Hand 85 70 20 110 100 F G H J K NN- E E E Given the following product structure, master production schedule, and inventory status below and assuming the requirements for each BOM item is 1: (a) develop a gross requirements plan for Item C; (b) develop a net requirements plan for Item C. Click the icon to view the product structure, master production schedule and inventory status. a) Develop a gross requirements plan for Items C. To do so, first find the gross requirements plans for its parents: items A and H. (Enter your responses as whole numbers) Week Item 1 2 3 4 5 6 7 9 10 11 12 A Gross req 8Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts