Question: a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow tie and average days past

a. Develop separate schedules by using the FCFS

a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow tie and average days past due.

Using the FCFS (first come, first served) decision rule for sequencing the customers, the order is:

Sequence 1 2 3 4 5
Customer

Using the EDD (earliest due date) decision rule for sequencing the customers, the order is (to resolve a tie, use the order in which the jobs were received):

Sequence 1 2 3 4 5
Customer

The average flow time and average days past due for each option are:

Rule Average Flow Time Average Days Past Due
EDD
FCFS

b. On the basis of average flow time, which rule gives the best schedule? EDD or FCFS

On the basis of average days past due, which rule give the best schedule? EDD or FCFS

Cumenty a company that designs Web sites has five customers in its backing The Sime since the order arrived, processing time, and promised due dates are given in the following table. The customers are ready to be scheduled loday, which is the start of day 100 Time Since Order Arrived (days ago) Processing Time (day) Due Date (days from Customer now 12 50 10 66 C 3 24 68 D 2 32 100 10 20 25 Develop separate schedules by using the FCFS and EDD ries. Compare the schedules on the basis of average flow time and average days du Using the FOFS (est come, first servel) decision nue for sequencing the customers, the onders 2 3 4 6 Sequence A Customer Y Y Y Y

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!