Question: a. Develop the project network b. What are the critical activities? c. What is the expected time to complete the project? d. Based only on
a. Develop the project network
G Building a backyard swimming pool consists of nine major activities. The activities and their immediate predecessors are shown. Activity A B D E F H | Immediate Assuming the A,B , B D DF E,G,H Predecessor project has the following times for the activities: C Activity Optimistic Most Probably Pessimistic 3 5 6 B 2 4 6 5 6 7 D 7 9 10 E N 4 6 4 2. F F 1 3 N 8 5 G 10 6 8 10 H 3 4 1 5 b. What are the critical activities?
c. What is the expected time to complete the project?
d. Based only on the critical path, what is the estimated probability that the project can be completed in 25 or fewer days?
e. Based on all the paths, what is the probability that the project can be completed in 25 days?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock