Question: A Differing Site Condition/Unforeseeable Physical Condition clause: Assigns all risk of latent site conditions to the contractor Is intended to alert the contractor to the

A Differing Site Condition/Unforeseeable Physical
A Differing Site Condition/Unforeseeable Physical Condition clause: Assigns all risk of latent site conditions to the contractor Is intended to alert the contractor to the risk of unanticipated site conditions so they can include an appropriate contingency cost in their bid Generally provides for direct cost damages but no delay or impact costs Assigns the risk of latent physical conditions at the site to the owner