Question: A) Draw a network diagram for this project with floats. Answer the following about the network diagram: B) What is the critical path? C) What
A) Draw a network diagram for this project with floats.
Answer the following about the network diagram:
B) What is the critical path?
C) What is the float of task C?
D) What is the float of task G?
E) What is the impact to the duration of the project if the duration of task N changes to 12 weeks?
F) What is the impact on the project's duration if the duration of task E increases by 5 weeks? What is the new critical path?
G) What is the impact on the project's duration if reducing the expected duration of H by 1 week and increasing the duration of task B by 15 weeks?
We have identified the following activities on a project. All durations are in weeks Task Duration Predecessor A B D E (1) F G H I J N M S M 7 5 00 19 8 6 3 160 5 15 5 5 9 + Start A Start B B, D B B G.C E F GH LI N SK