A) Draw a network diagram for this project with floats. Answer the following about the network diagram:
Fantastic news! We've Found the answer you've been seeking!
Question:
A) Draw a network diagram for this project with floats.
Answer the following about the network diagram:
B) What is the critical path?
C) What is the float of task C?
D) What is the float of task G?
E) What is the impact to the duration of the project if the duration of task N changes to 12 weeks?
F) What is the impact on the project's duration if the duration of task E increases by 5 weeks? What is the new critical path?
G) What is the impact on the project's duration if reducing the expected duration of H by 1 week and increasing the duration of task B by 15 weeks?
Related Book For
Operations Management Processes And Supply Chains
ISBN: 9781292409863
13th Global Edition
Authors: Lee Krajewski, Naresh Malhotra, Larry Ritzman
Posted Date: