Question: 7:02 Q1. From the table information below Draw the network diagram (Points 5) ii) Show ALL the network paths (Points 2) iii) Determine the Critical

7:02 Q1. From the table information below Draw the network diagram (Points 5) ii) Show ALL the network paths (Points 2) iii) Determine the Critical Path and the total days (Point 3) iv) Determine the float for each activity (Point 5) Activity Duration Dependency Start 0 (days) A 5 (days) Start B 2 (days) Start C 3 (days) A, B D 5 (days) Start E 6 (days) Start F 4 (days) DE G 2 (days) C, F H 5 (days) G 7 (days) G J 3 (days) H Finish 0 (days) 1 , J Q2. From the table shown Shown the network diagram and calculate the critical path (Points ii) Project duration (Point 1) iii) Float of task C (Point 1) iv) Early Start of task E (Point 1) Late Finish of Task A (Point 1) Activity Predecessor Duration A 0 5 B 0 6 C A D A, B B C, D, E De1.alphacollege.ca C