Question: a) Draw a project network diagram for the data in the following table b) Identify all the paths in the network diagram and their duration
a) Draw a project network diagram for the data in the following table
b) Identify all the paths in the network diagram and their duration
c) Identify the critical path. Why is the critical path important to project managers?
d) What is the project completion time? Justify your answer
Activity Activity Description Predecessor(s) Duration (Weeks) A 6 None A 2 2. Design prototype Obtain materials Order parts Manufacture parts Assembly 1 Assembly 2 Final Assembly A B D 3 F C 2 E D, F 4 G E E 1Step by Step Solution