Question: Draw a project network diagram for the data in the following table. Activity Activity Description Predecessor(s) Duration (Weeks) 6 A B C 2 Design prototype

Draw a project network diagram for the data in

Draw a project network diagram for the data in the following table. Activity Activity Description Predecessor(s) Duration (Weeks) 6 A B C 2 Design prototype Obtain materials Order parts Manufacture parts Assembly 1 Assembly 2 Final Assembly None A B D, F E F E G 3 2 4 1 a) Identify all the paths in the network diagram and their duration b) Identify the critical path. c) What is the project completion time? [ 4 Marks) (2 Marks] [2 marks]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!