Question: a) Draw an AON network diagram for the project. ? Determine the critical path of the project.? b) Calculate the expected time for all activities.

a) Draw an AON network diagram for the project. ? Determine the critical path of the project.? b) Calculate the expected time for all activities. ? What is the expected project completion duration? c) Calculate the variance of the critical path ? Estimate the probability that the project will be completed on or less than Month 26 (show your calculations)
The following table presents project information (time unit in months) Predecessors Activit y A B D E F G MOAL Pessimisti Duration 12 8 9 7 12 7 10 Optimisti Duration 7 4 5 4 8 3 5 Most likely Duration 10 5 7 5 10 4 8 A B B, D B, D E, F toomStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
