Question: Problem 1 (30 points) The following table presents project information (time unit in months) Activity Predecessors Pessimistic Duration Most likely Duration Optimistic Duration A ____

Problem 1 (30 points)

The following table presents project information (time unit in months)

Activity Predecessors

Pessimistic

Duration

Most likely Duration Optimistic Duration
A ____ 12 10 7
B ____ 8 5 4
C A 9 7 5
D B 7 5 4
E B, D 12 10 8
F B, D 7 4 3
G E, F 10 8 5

  1. Draw an AON network diagram for the project.
  2. Determine the critical path of the project.
  3. Calculate the expected time for all activities.
  4. What is the expected project completion duration?
  5. Calculate the variance of the critical path.
  6. Estimate the probability that the project will be completed on or less than Month 26 (show your calculations).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!