Question: Problem 1 (30 points) The following table presents project information (time unit in months) Activity Predecessors Pessimistic Duration Most likely Duration Optimistic Duration A ____
Problem 1 (30 points)
The following table presents project information (time unit in months)
| Activity | Predecessors | Pessimistic Duration | Most likely Duration | Optimistic Duration |
| A | ____ | 12 | 10 | 7 |
| B | ____ | 8 | 5 | 4 |
| C | A | 9 | 7 | 5 |
| D | B | 7 | 5 | 4 |
| E | B, D | 12 | 10 | 8 |
| F | B, D | 7 | 4 | 3 |
| G | E, F | 10 | 8 | 5 |
- Draw an AON network diagram for the project.
- Determine the critical path of the project.
- Calculate the expected time for all activities.
- What is the expected project completion duration?
- Calculate the variance of the critical path.
- Estimate the probability that the project will be completed on or less than Month 26 (show your calculations).