Question: a. draw project Network Diagram b. what completion date would you recommend (crashing) Question 2: Software Installation Project Activity Immediate Predecessor Normal Cost Crash Cost
a. draw project Network Diagram
Question 2: Software Installation Project Activity Immediate Predecessor Normal Cost Crash Cost S per Week Max Crash Possible A Normal Time (weeks) 5 8 10 4 - A A, B B B D E F G H I Crash Time (Weeks) 3 7 8 3 2 6 2 5 7 $2,000 $5,000 $10,000 $3,000 $4,000 $8,000 $2,000 $6,000 $7,000 3 9 $4,000 $8,000 $12,000 $7,000 $5,00 $14,000 $2,000 $9,000 $15,000 D E, F G CF 2 8 9 Penalty: $1000 per week beyond 25 weeks Indirect Project Costs: $ 2500 per week b. what completion date would you recommend (crashing)