Question: a. Draw the precedence diagram using the Activity On Arrow (AOA) approach. b. Determine which activities should be crashed to shorten the project by 2

a. Draw the precedence diagram using the Activity

a. Draw the precedence diagram using the Activity On Arrow (AOA) approach.

b. Determine which activities should be crashed to shorten the project by 2 weeks as cheaply as possible.

First Crash Second Crash We have the following list of activities for a project and crashing costs: Path Activity Immediate Duration (weeks) Predecessor Top A 5 B A 6 B, E 3 $8 $7 $14 $10 $9 $15 Middle D E D B, E 3 7 3 $9 $8 $14 $11 $9 $15 Bottom $10 F G H F G 5 5 5 $11 $12 $15 $13 $14

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!